EAST 185TH STREET REHABILITATION
NOTTINGHAM ROAD TO LAKE ERIE

MAINTAINING TRAFFIC

While the improvements are being constructed along East 185th Street, southbound traffic will be detoured to East 200th Street and northbound traffic will be maintained between Villaview Road and Lake Erie. The detour route will be signed so that drivers are able to navigate southbound East 185th Street by following temporary detour signs. Two-way traffic will be maintained between Nottingham Road to Villaview Road.

Access to residences and businesses will be maintained throughout construction. The contractor will be required to coordinate with the schools and hospitals. Access to the I-90 ramps will be maintained at all times except for short duration closures during off peak hours. Side streets will be closed in an alternating sequence for intersection construction. Part-width construction will be required for the intersections of Villaview Road, Neff Road and Lakeshore Boulevard. 

Construction will occur in one full and one partial construction season, and in two stages. Each stage of construction will have two phases  as described and shown below. Stage 1 construction will be between Nottingham Road and Abby Avenue. Stage 2 Construction will be between Abby Avenue and Lake Erie.

STAGE 1 PHASING

Stage 1 - Phase 1: Villaview Road to Abby Avenue

During Stage 1 – Phase 1 of construction, the contractor will build the east side of the road while maintaining northbound traffic on the west side of the road. One-way northbound traffic will be maintained between Villaview Road and Abby Avenue. Southbound traffic will be detoured. On-street parking will be maintained on the west side. As shown in the exhibit below, the work zone (where the construction is happening) will be separated from the northbound travel lane by orange barrels. 

Stage 1 - Phase 2: Villaview Road to Abby Avenue

During Stage 1 – Phase 2 of construction, the contractor will build the west side of the road while maintaining northbound traffic on the east side of the road. One-way northbound traffic will be maintained between Villaview Road and Abby Avenue. Southbound traffic will be detoured. On-street parking will be maintained on the east side. As shown in the exhibit below, the work zone (where the construction is happening) will be separated from the northbound travel lane by orange barrels. 

Stage 1 - Phase 1a: Nottingham Road to Villaview Road

During Stage 1 – Phase 1a of construction, the contractor will build the east side of the road while maintaining two-way traffic on the west side of the road. As shown in the exhibit below, the work zone (where the construction is happening) will be separated from the travel lanes by orange barrels. 

Stage 1 - Phase 1b: Nottingham Road to Villaview Road

During Stage 1 – Phase 1b of construction, the contractor will build the middle section of the road while maintaining two-way traffic on the outsides of the road. As shown in the exhibit below, the work zone (where the construction is happening) will be separated from the travel lanes by orange barrels. 

Stage 1 - Phase 2: Nottingham Road to Villaview Road

During Stage 1 – Phase 2 of construction, the contractor will build the west side of the road while maintaining two-way traffic on the east side of the road. As shown in the exhibit below, the work zone (where the construction is happening) will be separated from the travel lanes by orange barrels. 

STAGE 2 PHASING

Stage 2 - Phase 1: Abby Avenue to Lake Erie

During Stage 2 – Phase 1 of construction, the contractor will build the west side of the road while maintaining northbound traffic on the east side of the road. One-way northbound traffic will be maintained between Abby Avenue and Lake Erie. Southbound traffic will be detoured. On-street parking will be maintained on the east side from Abby Avenue to Lakeshore Boulevard. As shown in the exhibit below, the work zone (where the construction is happening) will be separated from the northbound travel lane by orange barrels. 

Stage 2 - Phase 2: Abby Avenue to Lake Erie

During Stage 2 – Phase 2 of construction, the contractor will build the east side of the road while maintaining northbound traffic on the west side of the road. One-way northbound traffic will be maintained between Abby Avenue and Lake Erie. Southbound traffic will be detoured. On-street parking will be maintained on the west side from Abby Avenue to Lakeshore Boulevard. As shown in the exhibit below, the work zone (where the construction is happening) will be separated from the northbound travel lane by orange barrels.